Evaluation database
Evaluation report
2003 BOL: Evaluation of Sida-Funded Projects Through UNICEF - Bolivia 1989 - 2002
Author: Dahl-Østergaard, T.; Rojas, R.; Moore, D.; Rozo, P.
Executive summary
Background:
Sweden has been one of the most important donors to the implementation of UNICEF programmes in Bolivia, providing a total of SEK 165 million since 1989. The support has been focused on three projects: the Bilingual Education Project, the Health Education Project, and PRO ANDES. These comprise 11 separate components, all of which are referred to by Sida as the Social Development Programme.
Purpose/Objective:
The regular reporting on the Programme has not monitored the impact of the activities. Hence, in view of the overall poverty reduction objective of Swedish development assistance, the main purpose of the present evaluation was to assess the poverty reduction impact and likely sustainability of the Programme during the 13-year period from 1989 to 2002.
Methodology:
This evaluation is based on primary and secondary data collected between 7th and 22nd October 2002, when the team worked together in Bolivia. Fieldwork was carried out in the departments of Potosi, Cochabamba and Chuquisaca.
As it was impossible to undertake a quantitative assessment of the impact, it was decided to focus on the perceptions of the beneficiaries. The sustainability of project interventions focused on the coherence between project initiatives and the priorities and poverty escape strategies of the poor themselves, and the coherence between project interventions and the policies at national, departmental and municipal levels.
Findings and Conclusions:
The overall conclusion of the evaluation team is that the greatest likelihood of sustainability is found in the projects that have become integrated with national policies and programmes (EIB and health). On the other hand, the activities that have been implemented by UNICEF more or less in isolation (Yuyay Jap'ina, Wawa Wasi, Kallpa Wawa) have substantial limitations insofar as sustainability.
However, while it is the preferable route to follow, the anchoring of UNICEF activities within the framework of public policies is no guarantee of sustainability. The financial and human resources available to the involved government entities impose the limit on their ability to ensure sustainability.
The economic crisis, and its manifestations at both government and community levels, underscores the pervasive and substantial dependency on external donor support in Bolivia. This has developed almost to the point of becoming a permanent state of affairs. As one mayor said when he was confronted with the fact that UNICEF would withdraw from his municipality at the end of the year and asked how he would ensure the continuation of activities: "They will continue, but I don't know how. It is always possible to get funds from international donors."
The Bolivian Government, however, is not only suffering from economic problems. The political culture and traditions that result in frequent changes of staff at all levels is a serious threat to the likelihood of achieving sustainability in any programme implemented through the government structures. If a UNICEF programme is not integrated with national policies and programmes, then it becomes all the more important to ensure an optimal integration with livelihood strategies of the target groups. This would call for tailor-made solutions at the project level, rather than the application of blueprint options regarding the design of a water system, for example. Ongoing impact monitoring could help in keeping project activities in line with the livelihood strategies, which is likely to change over time, of the target groups. Finally, the attention given to the termination of projects is inadequate. It appears that projects are finished as a function of the funding available or the duration of the project period that is defined for an intervention. One of the mayors interviewed stated the problem very clearly: there is a lack of an exit strategy.
Other Conclusions:
The Social Development Programme has contained a mix of service delivery and institutional development/capacity building. The balance tilts towards an over-weight of service delivery, but it is difficult to aggregate the numerous project activities over the 13-year period evaluated.
With some exceptions - EIB being the most notable one - UNICEF has not been sufficiently focused on the launching of pilot activities that could be tested with the explicit purpose of possible scaling up into government policies and programmes.
Recommendations:
UNICEF should, in the future, apply their considerable expertise to launch and test - in close collaboration with the Government of Bolivia - innovative pilot activities in areas of Government priority and community demands. The conditions under which possible scaling up into government policies and programmes should be done, should be made explicit from the outset. In other words, a clear Government commitment should be established before a new programme is launched.
Ideally, the exit strategy of any programme or project activity should be formulated already in the design stage. As a general rule, project activities should not be terminated before the objectives have been reached; if this is done, it is basically abandonment, not the achievement of development objectives. This kind of phase-out strategy necessitates well-defined project impact targets and regular monitoring of their achievement.
One project component would appear to merit special attention: the Wawa Wasi. This component is highly regarded among the beneficiaries and, in the view of the evaluation team, this is perhaps the component that has achieved the most significant level of impact. Yet, it is also one of the components with the least likelihood of attaining sustainability in the services delivered. Somehow, this paradox calls for special consideration.
Finally, consideration should be given to the possibility of negotiating conditions and contract-like agreements with the municipalities and the Government to ensure the continuation and sustainability of some of the project components that are about to terminate in the near future.
Full report in PDF
PDF files require Acrobat Reader.
Report information
Date:
2003
Region:
TACRO
Country:
Bolivia
Type:
Evaluation
Theme:
Program Review
Partners:
PIDB:
Follow-up:
Language:
English
Sequence Number:
2003/800


















